Construction of a Silo rack and a pallet rack - part 2.
Last week we completed the last but one stage of the project. Because we were ahead of schedule, we had to slow down our works for a dozen or so days to make it possible for other teams to complete their work in time.
All the works on the lower pallet racks were also finished. Stacker cranes are already installed in these pallet racks.
In the Silo rack, the stacker cranes will be installed within the next few days.
Monday, 28 October 2013