Construction of SILO shelving in the Sugar Factory pt. 2
In the past several days we have erected the first elements of the shelving, the work is still progressing relatively slowly due to the necessity of frequent detailed measurements of the alignment of the pillars on all planes.
As soon as the first blocks will be set, the pace of work will significantly increase; in the meantime the prefabrication of structural components and drilling continues.
Thursday, 7 July 2011