Construction of SILO shelving in the Sugar Factory pt. 4
Thanks to the favourable weather conditions during this month, the works progressed significantly.
The shelving elements and the roof of the hall are erected on an ongoing basis.
All the 5 corridors, in which the automatic stacker cranes will be operating, are clearly visible and, considering that the structure is 36 m high, one can estimate the magnitude of the work already accomplished.
Unfortunately, as it is with this type of construction, the pace of work is strongly dependent on the weather conditions, but we hope that they will continue to be so, that we can complete the construction before the end of October.
Wednesday, 12 September 2012