Construction of SILO shelving in the Sugar Factory pt. 5
A few weeks before the construction is planned to be finished, one of the last building stages has begun, that is the installation of the so-called pallet exit area. These works are fairly difficult, as the components have to be installed individually due to the restricted space for handling the large construction elements.
At present, 24 of our employees are working at the site, most of whom are involved in the current building stage, while others are already laying the foundations for the feet of the shelves.
In a few days also the welding of the rails for the upper stacker cranes and the preparation of the stacker cranes for their installation in the shelving shall begin.
Monday, 17 October 2011