Construction of SILO shelving in the Sugar Factory pt. 1
Another big project started in mid-May. This time the structure will be 36 m high and the goods will be stored with 7 automatic stacker cranes.
As usual, the work began with site preparation, surveying, and layout of holes for anchoring the structure.
At present, drilling and prefabrication of structural elements are at an advanced stage.
Over the next two weeks the number of employees will increase to approximately 20, which will significantly increase the pace of work.
Monday, 6 June 2011