Shelving construction in the Sugar Plant pt. 2
At the end of October the process of putting stacker cranes in the shelving corridors was finished. As the shelving structure is complete in over 80% of cases, the tower crane will be dismantled in the second week of November because there is no longer place for it on the hall floor. The last stage of the shelving construction will be carried out with the use of a mobile crane.
Part of the roof is already in place and, therefore, we have started another stage consisting in installing conveyors in the pallet entrance/exit area. At the same time, we will be making concrete foundations for the shelving and preparing stack crane guide rails.
Thursday, 1 November 2012