Construction of SILO shelving in the HDF boards factory pt. 3
Due to the approaching deadline for completion of construction, the works on the shelves are close to the end. At the moment about 3/4 of the rack are completed.
Our staff fitted and welded the top and bottom rail, so that a stacker crane could be installed. This was one of the most complicated operations throughout the entire construction process. A structure of nearly 30 tons had to be lifted with a crane and set with a precision of a few millimetres.
Next, we plan to make the concrete floor levelling underneath the stacker crane rail and then to complete the rack structure.
Tuesday, 5 April 2011